Article 29 - Implementation of decisions under this Regulation

Article 29

Implementation of decisions under this Regulation

1.  
National resolution authorities shall take the necessary action to implement decisions referred to in this Regulation, in particular by exercising control over the entities and groups referred to in Article 7(2), and the entities and groups referred to in Article 7(4)(b) and (5) where the conditions for the application of those paragraphs are met, by taking the necessary measures in accordance with Article 35 or 72 of Directive 2014/59/EU and by ensuring that the safeguards provided for in that Directive are complied with. National resolution authorities shall implement all decisions addressed to them by the Board.

For those purposes, subject to this Regulation, they shall exercise their powers under national law transposing Directive 2014/59/EU and in accordance with the conditions laid down in national law. National resolution authorities shall fully inform the Board of the exercise of those powers. Any action they take shall comply with the Board's decisions pursuant to this Regulation.

When implementing those decisions, the national resolution authorities shall ensure that the applicable safeguards provided for in Directive 2014/59/EU are complied with.

2.  

Where a national resolution authority has not applied or has not complied with a decision by the Board pursuant to this Regulation or has applied it in a way which poses a threat to any of the resolution objectives under Article 14 or to the efficient implementation of the resolution scheme, the Board may order an institution under resolution:

(a) 

in the event of action pursuant to Article 18, to transfer to another person specified rights, assets or liabilities of an institution under resolution;

(b) 

in the event of action pursuant to Article 18, to require the conversion of any debt instruments which contain a contractual term for conversion in the circumstances provided for in Article 21;

(c) 

to adopt any other necessary action to comply with the decision in question.

The Board shall adopt a decision referred to in point (c) of the first subparagraph only if the measure significantly addresses the threat to the relevant resolution objective or to the efficient implementation of the resolution scheme.

Before deciding to impose any measure the Board shall notify the national resolution authorities concerned and the Commission of the measure it intends to take. That notification shall include details of the envisaged measures, the reasons for those measures and details of when the measures are intended to take effect.

The notification shall be made not less than 24 hours before the measures are to take effect. In exceptional circumstances where it is not possible to give 24 hours' notice, the Board may make the notification less than 24 hours before the measures are intended to take effect.

3.  
The institution under resolution shall comply with any decision taken referred to in paragraph 2. Those decisions shall prevail over any previous decision adopted by the national resolution authorities on the same matter.
4.  
When taking action in relation to issues which are subject to a decision taken pursuant to paragraph 2, national resolution authorities shall comply with that decision.
5.  
The Board shall publish on its official website either a copy of the resolution scheme or a notice summarising the effects of the resolution action, and in particular the effects on retail customers. The national resolution authorities shall comply with the applicable procedural obligations provided for in Article 83 of Directive 2014/59/EU.