Article 89
1.
Until 18 June 2021, the
clearing obligation set out in Article 4 shall not apply to
OTC derivative contracts that are objectively measurable as reducing investment risks that directly relate to the financial solvency of
pension scheme arrangements, and to entities established to provide compensation to members of such arrangements in case of default.
The clearing obligation set out in Article 4 shall not apply to OTC derivative contracts as referred to in the first subparagraph of this paragraph entered into by pension scheme arrangements from 17 August 2018 until 16 June 2019.
The OTC derivative contracts, which would otherwise be subject to the clearing obligation under Article 4, entered into by those entities during this period shall be subject to the requirements laid down in Article 11.
2.
In relation to
pension scheme arrangements referred to in Article 2(10)(c) and (d) the exemption referred to in paragraph 1 of this Article shall be granted by the relevant
competent authority for types of entities or types of arrangements. After receiving the request, the
competent authority shall notify ESMA and EIOPA. Within 30 calendar days of receipt of the notification ESMA, after consulting EIOPA, shall issue an opinion assessing compliance of the type of entities or the type of arrangements with Article 2(10)(c) or (d) as well as the reasons why an exemption is justified due to difficulties in meeting the variation margin requirements. The
competent authority shall only grant an exemption where it is fully satisfied that the type of entities or the type of arrangements complies with Article 2(10)(c) or (d) and that they encounter difficulties in meeting the variation margin requirements. The
competent authority shall adopt a decision within ten working days of receipt of ESMA’s opinion, taking due account of that opinion. If the
competent authority does not agree with ESMA’s opinion, it shall give full reasons in its decision and shall explain any significant deviation therefrom.
ESMA shall publish on its website a list of types of entities and types of arrangements referred to in Article 2(10)(c) and (d) which has been granted an exemption in accordance with the first subparagraph. To further strengthen consistency in supervisory outcomes, ESMA shall conduct a peer review of the entities included on the list every year in accordance with Article 30 of Regulation (EU) No 1095/2010.
3.
A
CCP that has been authorised in its Member State of establishment to provide
clearing services in accordance with the national law of that Member State before all the regulatory technical standards under Articles 4, 5, 8 to 11, 16, 18, 25, 26, 29, 34, 41, 42, 44, 45, 46, 47, 49, 56 and 81 are adopted by the Commission, shall apply for authorisation under Article 14 for the purposes of this Regulation within six months of the date of entry into force of all the regulatory technical standards under Articles 16, 25, 26, 29, 34, 41, 42, 44, 45, 47 and 49.
A CCP established in a third country, which has been recognised to provide clearing services in a Member State in accordance with the national law of that Member State before all the regulatory technical standards under Articles 16, 26, 29, 34, 41, 42, 44, 45, 47 and 49 are adopted by the Commission, shall apply for recognition under Article 25 for the purposes of this Regulation within six months of the date of entry into force of all the regulatory technical standards under Articles 16, 26, 29, 34, 41, 42, 44, 45, 47 and 49.
3a.
ESMA shall not exercise its powers pursuant to Article 25(2a), (2b) and (2c) until the date of entry into force of the delegated acts referred to in the second subparagraph of Article 25(2a) and in Article 25a(3) and, in relation to
CCPs for which ESMA has not adopted a recognition decision pursuant to Article 25 before 1 January 2020, until the date of entry into force of the relevant implementing act referred to in Article 25(6).
3b.
ESMA shall establish and manage a college pursuant to Article 25c for all
CCPs recognised in accordance with Article 25 before 1 January 2020 within four months from the date of entry into force of the delegated act referred to in the second subparagraph of Article 25(2a).
3c.
ESMA shall review the recognition decisions adopted pursuant to Article 25(1) before the date of entry into force of the delegated acts referred to in the second subparagraph of Article 25(2a) and in Article 25a(3) within 18 months from the date of entry into force of the delegated act referred to in the second subparagraph of Article 25(2a), in accordance with Article 25(5).
Where, following the review referred to in the first subparagraph of this paragraph, ESMA determines that a CCP recognised before 1 January 2020 should be classified as a Tier 2 CCP in accordance with Article 25(2a), ESMA shall set an appropriate adaptation period which shall not exceed 18 months within which the CCP must comply with the requirements referred to in Article 25(2b). ESMA may extend the adaptation period up to an additional six months upon the reasoned request of the CCP or any of the competent authorities responsible for the supervision of clearing members established in the Union, where such extension is justified by exceptional circumstances and by the impact on the clearing members established in the Union.
4.
Until a decision is made under this Regulation on the authorisation or recognition of a
CCP, the respective national rules on authorisation and recognition of
CCPs shall continue to apply and the
CCP shall continue to be supervised by the
competent authority of its Member State of establishment or recognition.
5.
Where a
competent authority authorised a
CCP to clear a given
class of derivatives in accordance with the national law of its Member State before all the regulatory technical standards under Articles 16, 26, 29, 34, 41, 42, 45, 47 and 49 are adopted by the Commission, the
competent authority of that Member State shall notify ESMA of that authorisation within one month of the date of entry into force of the regulatory technical standards under Article 5(1).
Where a competent authority recognised a CCP established in a third country to provide clearing services in accordance with the national law of its Member State before all the regulatory technical standards under Articles 16, 26, 29, 34, 41, 42, 45, 47 and 49 are adopted by the Commission, the competent authority of that Member State shall notify ESMA of that recognition within one month of the date of entry into force of the regulatory technical standards under Article 5(1).
6.
A
trade repository that has been authorised or registered in its Member State of establishment to collect and maintain the records of derivatives in accordance with the national law of that Member State before all the regulatory and implementing technical standards under Articles 9, 56 and 81 are adopted by the Commission, shall apply for registration under Article 55 within six months of the date of entry into force of those regulatory and implementing technical standards.
A trade repository established in a third country, which is allowed to collect and maintain the records of derivatives in a Member State in accordance with the national law of that Member State before all the regulatory and implementing technical standards under Articles 9, 56 and 81 are adopted by the Commission, shall apply for recognition under Article 77 within six months of the date of entry into force of those regulatory and implementing technical standards.
7.
Until a decision is made under this Regulation on the registration or recognition of a
trade repository, the respective national rules on authorisation, registration and recognition of
trade repositories shall continue to apply and the
trade repository shall continue to be supervised by the
competent authority of its Member State of establishment or recognition.
8.
A
trade repository that has been authorised or registered in its Member State of establishment to collect and maintain the records of derivatives in accordance with the national law of that Member State before the regulatory and implementing technical standards under Articles 56 and 81 are adopted by the Commission, can be used to meet the reporting requirement under Article 9 until the time a decision is made on the registration of the
trade repository under this Regulation.
A trade repository established in a third country which has been allowed to collect and maintain the records of derivatives in accordance with the national law of a Member State before all the regulatory and implementing technical standards under Articles 56 and 81 are adopted by the Commission, can be used to meet the reporting requirement under Article 9 until the time a decision is made on the recognition of the trade repository under this Regulation.
9.
Notwithstanding Article 81(3)(f), where no international agreement is in place between a third country and the Union as referred to in Article 75, a
trade repository may make the necessary information available to the relevant authorities of that third country until 17 August 2013 provided that it notifies ESMA.