Article 32i - Process of cooperation between the competent authority and the resolution authority when granting the permission referred to in Article 78a of Regulation (EU) No 575/2013

Article 32i

Process of cooperation between the competent authority and the resolution authority when granting the permission referred to in Article 78a of Regulation (EU) No 575/2013

1.  
Where a complete application for a prior permission, including the general prior permission referred to in Article 78a(1), second subparagraph, of Regulation (EU) No 575/2013, is submitted by an institution, the resolution authority shall promptly transmit that application to the competent authority, including the information referred to in Article 32d and, where applicable, Article 32e, Article 32f or Article 32h.
2.  
At the same time of the transmission of the information referred to in paragraph 1, the resolution authority shall make a request for consultation to the competent authority on the application received, which shall include the reciprocal exchange of any other relevant information for the assessment of the application by the resolution or competent authority.
3.  
The competent authority and the resolution authority shall agree on an adequate time limit for providing a response to the consultation referred to in paragraph 2, which shall not exceed three months from the moment of receipt of the request for consultation and that shall be reduced to two months where the consultation concerns the renewal of a general prior permission pursuant to Article 32f or a general prior permission pursuant to Article 32h. The resolution authority shall consider the views received from the competent authority before taking a decision on the permission.
4.  
Where the agreement of the competent authority is required in accordance with Article 78a(1), point (b), of Regulation (EU) No 575/2013, the resolution authority shall communicate to the competent authority, within two months from the request for consultation referred to in paragraph 2, or within one month where the consultation concerns the renewal of a general prior permission pursuant to Article 32f or a general prior permission pursuant to Article 32h, the proposed margin by which, following the action referred to in Article 77(2) of that Regulation, the resolution authority considers necessary that the own funds and eligible liabilities of the institution must exceed its requirements.
5.  
Within three weeks or, where the consultation concerns the renewal of a general prior permission pursuant to Article 32f or a general prior permission pursuant to Article 32h, within two weeks, after receiving the communication referred to in paragraph 4, the competent authority shall transmit its written agreement to the resolution authority. In the event that the competent authority disagrees or partially disagrees with the resolution authority, it shall inform the resolution authority within that period, stating its reasons.
6.  
By way of derogation from paragraph 3, where the agreement of the competent authority is required in accordance with Article 78a(1), point (b), of Regulation (EU) No 575/2013, the competent authority shall provide a response to the consultation referred to in paragraph 2 at the same time as the transmission of its written agreement to the resolution authority referred to in paragraph 5.
7.  
By way of derogation from paragraphs 3 to 6, where the maximum time period for processing the application referred to in paragraph 1 is shorter than four months in accordance with Article 32g, paragraphs 3 or 4, the periods of time referred to in paragraphs 3, 4 and 5 shall be agreed between the resolution authority and the competent authority taking into account the relevant maximum time period.
8.  
The resolution authority and the competent authority shall endeavour to reach the agreement referred to in paragraph 5 in order to ensure that the application referred to in paragraph 1 is processed in any event within the period of time referred to in Article 32g, paragraphs 1, 2, 3 or 4.
9.  
The resolution authority shall communicate to the competent authority the decision taken on the permission without undue delay. The resolution authority shall also inform the competent authority in case of withdrawal of the general prior permission where an institution breaches any of the criteria provided for the purposes of that permission.